Analisis Overall Equipment Effectiveness dalam Penerapan Total Productive Maintenance Pada Mesin Flow Mixer di PT ASI

Authors

  • Wilarso Universitas Muhammadiyah Cileungsi
  • Bayu Hamengku Rizkiansyah Universitas Muhammadiyah Cileungsi, Indonesia
  • Asep Dharmanto Universitas Muhammadiyah Cileungsi, Indonesia
  • Asep Saepudin Universitas Muhammadiyah Cileungsi, Indonesia
  • Mujiarto Universitas Muhammadiyah Tasikmalaya, Tasikmalaya, Indonesia

DOI:

https://doi.org/10.36499/jim.v22i1.15469

Keywords:

Total Productive Maintenance, Overall Equipment Effectiveness, Six Big Losses, Flow Mixer

Abstract

Improving machine productivity and effectiveness is a crucial factor in maintaining the competitiveness of manufacturing companies. One approach to improving equipment performance is Total Productive Maintenance (TPM), with Overall Equipment Effectiveness (OEE) as the primary indicator. This study aims to analyze the effectiveness of the Flow Mixer machine at PT ASI's Mold Shop Department based on its OEE value, which comprises availability, performance, and quality. It also identifies the dominant factors causing low machine effectiveness using the Six Big Losses approach and a fishbone diagram. The research data were obtained from production data, planned and unplanned downtime, the number of defective products, and machine operating time during September–November 2025. The calculation results show that the Flow Mixer machine's OEE values ​​were 66% (September), 68% (October), and 68% (November), respectively, which are still below the world-class OEE standard of 85%. The main factors influencing the low OEE are breakdowns and process defect loss. Improvement proposals are based on the eight pillars of TPM, which focus on improving machine maintenance, operator skills, and standardizing work procedures. Implementation of the proposed improvements in December resulted in an increase in the OEE value to 72%. The results of this study demonstrate that consistent TPM implementation can improve the effectiveness of the Flow Mixer machine and the productivity of the production process.

References

[1] Y. Siswanto, T. Hidayat, and D. R. S. Budi, “Analisis Total Productive Maintenance Overall Equipment Effectiveness Moulding PMS Line,” J. Teknol. dan Manaj., vol. 21, no. 2, 2023, doi: 10.52330/jtm.v21i2.127. https://doi.org/10.52330/jtm.v21i2.127

[2] M. B. Anthony, “Analisis Penerapan Total Productive Maintenance (TPM) Menggunakan Overall Equipment Efectiveness (OEE) Dan Six Big Losses Pada Mesin Cold Leveller PT. KPS,” JATI UNIK J. Ilm. Tek. dan Manaj. Ind., vol. 2, no. 2, 2019, doi: 10.30737/jatiunik.v2i2.333. https://doi.org/10.30737/jatiunik.v2i2.333

[3] N. C. Dewi, “Analisis Penerapan Total Productive Maintenance (TPM) Dengan Perhitungan Overall Equipment Efectiveness (OEE) Dan Six Big Losses Mesin Cavitec Pt. Essentra Surabaya (Studi Kasus Pt. Essentra),” Ind. Eng. Online J., vol. 4, no. 4, 2022.

[4] P. Purwanto, Subekti Subekti, Abdul Hamid, and Nur Indah, “Identify damage to the mixer motor on the banbury machine using the vibration method,” JTTM J. Terap. Tek. Mesin, vol. 5, no. 1, 2024, doi: 10.37373/jttm.v5i1.890. https://doi.org/10.37373/jttm.v5i1.890

[5] A. Samadhiya and R. Agrawal, “Total productive maintenance and sustainability performance: resource-based view perspective,” Benchmarking, vol. 31, no. 7, 2024, doi: 10.1108/BIJ-10-2022-0635. https://doi.org/10.1108/BIJ-10-2022-0635

[6] H. Suliantoro, N. Susanto, H. Prastawa, I. Sihombing, and A. Mustikasari, “PENERAPAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DAN FAULT TREE ANALYSIS (FTA) UNTUK MENGUKUR EFEKTIFITAS MESIN RENG,” J@ti Undip J. Tek. Ind., vol. 12, no. 2, 2017, doi: 10.14710/jati.12.2.105-118. https://doi.org/10.14710/jati.12.2.105-118

[7] A. V. Prasmoro and M. Ruslan, “Analisis Penerapan Total Productive Maintenance (TPM) dengan Metode Overall Equipment Effectiveness (OEE) pada Mesin Kneader (Studi Kasus PT. XYZ),” J. Ind. Eng. Syst., vol. 1, no. 1, 2020, doi: 10.31599/jies.v1i1.167. https://doi.org/10.31599/jies.v1i1.167

[8] I. Nursanti and Y. Susanto, “Analisis Perhitungan Overall Equipment Effectiveness (OEE) pada Mesin Packing untuk Meningkatkan Nilai Availability Mesin,” J. Ilm. Tek. Ind., vol. 13, no. 1, 2014.

[9] R. F. Prabowo, H. Hariyono, and E. Rimawan, “Total Productive Maintenance (TPM) pada Perawatan Mesin Grinding Menggunakan Metode Overall Equipment Effectiveness (OEE),” J. Ind. Serv., vol. 5, no. 2, 2020, doi: 10.36055/jiss.v5i2.8001. ttps://doi.org/10.36055/jiss.v5i2.8001

[10] A. P. Aziz and I. Feriadi, “Measuring the reliability of hydraulic production equipment for tin suction vessels using the OEE and MTBS methods,” vol. 7, no. 1, pp. 146–156, 2026, doi: 10.37373/jttm.v7i1.2058.

[11] A. Wahid, “Penerapan Total Productive Maintenance (TPM) Produksi Dengan Metode Overall Equipment Effectiveness (OEE) Pada Proses Produksi Botol (PT. XY Pandaan – Pasuruan),” J. Teknol. DAN Manaj. Ind., vol. 6, no. 1, 2020, doi: 10.36040/jtmi.v6i1.2624. https://doi.org/10.36040/jtmi.v6i1.2624

[12] D. H. Triwardani, A. Rahman, and C. F. M. Tantrika, “Analisis Overall Equipment Effectiveness (OEE) Dalam Meminimalisi Six Big Losses Pada Mesin Produksi Dual Filters DD07,” J. Rekayasa dan Manaj. Sist. Ind., vol. 1, no. 2, 2013.

[13] L. E. Puspita and E. P. Widjajati, “PENGUKURAN EFEKTIVITAS MESIN LATEXING PADA PRODUKSI KARPET PERMADANI DENGAN MENGGUNAKAN METODE OVERALL EQUIPMENT EFFECTIVENESS (OEE) DAN OVERALL RESOURCE EFFECTIVENESS (ORE) DI PT. XYZ,” JUMINTEN, vol. 2, no. 4, 2021, doi: 10.33005/juminten.v2i4.295. https://doi.org/10.33005/juminten.v2i4.295

[14] I. Rizkia, H. Adianto, and Y. Yuniati, “Penerapan Metode Overall Equipment Effectiveness (Oee) Dan Failure Mode and Effect Analysis (Fmea) Dalam Mengukur Kinerja Mesin Produksi Winding Nt-880N Untuk Meminimasi Six Big Losses *,” J. Online Inst. Teknol. Nas., vol. 3, no. 04, 2015.

[15] Muhammad Nanda Ali Waket and Moh. Jufriyanto, “Analisis Overall Equipment Effectiveness (OEE) dan Six Big Losses pada Mesin Coiling di Proses Produksi Coil Spring Plant 3A,” J. Teknol. dan Manaj. Ind. Terap., vol. 4, no. 4, 2025, doi: 10.55826/jtmit.v4i4.1401. https://doi.org/10.55826/jtmit.v4i4.1401

[16] E. K. Karmilawati, K. M. Mulyono, and S. N. Nugroho, “Pendekatan OEE (Overall Equipment Effectiveness) Untuk Mengurangi Losses Pada Mesin Moulding Cerex,” J. Optimasi Tek. Ind., vol. 3, no. 2, 2021, doi: 10.30998/joti.v3i2.8576. https://doi.org/10.30998/joti.v3i2.8576

[17] E. Tammya and D. Herwanto, “Analisis Efektivitas Mesin Debarker Dengan Menggunakan Metode Overall Equipment Effectiveness (OEE) Di PT. XYZ Kuningan, Jawa Barat,” J. Sains, Teknol. dan Ind., vol. 19, no. 1, 2021.

[18] G. Asprilla, “Meningkatkan Kinerja Mesin Extrude Hydron Menggunakan Metode Preventive Maintenance,” JTTM J. Terap. Tek. Mesin, vol. 1, no. 1, 2020, doi: 10.37373/msn.v1i1.15. https://doi.org/10.37373/msn.v1i1.15

Additional Files

Published

2026-04-28

How to Cite

Wilarso, Bayu Hamengku Rizkiansyah, Asep Dharmanto, Asep Saepudin, & Mujiarto. (2026). Analisis Overall Equipment Effectiveness dalam Penerapan Total Productive Maintenance Pada Mesin Flow Mixer di PT ASI. Jurnal Ilmiah Momentum, 22(1), 15–27. https://doi.org/10.36499/jim.v22i1.15469